First in BC: 62 feet wide highway paving with echelon of 4 pavers side-by-side


Date Posted : September 18, 2023

Print| Email a Friend| Back


ALL ROADS has gained this contract for 4th year in a row. With all 4 phases put together, we resurfaced over 300 lane kilometers of the section of Hwy 1, and produced and laid down 240,000 tons of asphalt.


Asphalt Resurfacing Highway 1 Coquitlam Area (62.4 LANE KM)


This project is for the Ministry of Transportation and Infrastructure of British Columbia and covers the Highway 1 section from Brunette River Bridge to Port Mann Bridge in Coquitlam area,

Technologies used on this project include GPS, LPS & PaveLink Set-up for Scanning, Design and real-time tracking including load times, truck travel routes, asphalt usage, mat temperature, rolling pattens, and densities.

All Roads Flyover:

Completion date: October 2023

  • 50,498 Metric Tonnes of Asphalt Paving
  • 47,000 m2 of Full/Variable Depth Asphalt Milling
  • 19,416 LM of Concrete Barrier Removal & Replacement
  • 10 Crash Attenuators
  • Extensive Quality Assurance
  • Full GPS LPS Milling, Paving & PaveLink
  • Extensive Traffic Management & Control

Client:

  • Ministry of Transportation and Infrastructure – Vincent Ong
    Ph: 1-236-862-0601

Project Supervisor:

  • Ministry of Transportation and Infrastructure - Renato Suarez
    Ph: 1-778-621-2030

Project Associates:

  • Kontur Geotechnical
  • Eagle West Cranes