Centennial Expansion Partners - Asphalt Concrete Paving - CEPSSAP Project


Date Posted : April 1, 2023

Print| Email a Friend| Back


GPS & LPS Set-ups for full project scanning & design assistance which we have utilized in our full depth milling, fine grading, and multi-lift asphalt paving work. GPS Design was also utilized SSAP Roads Concrete Curb.



Project #: 211176

Contract Value: $17,650,323.53

Status: Completed

Start Date: Summer 2021

Completion Date: Spring 2023

Project Scope Highlights:

  • 130,000 Metric Tonnes of Asphalt Paving
  • 130,000m2 of Full Depth Asphalt Milling
  • 200,000m2 of Granular Base Preparation
  • 3500 LM of Concrete Curb
  • 2000 m2 of Concrete Flatwork Including Mountable Concrete Roundabouts & Security Islands
  • Extensive Quality Assurance
  • Full GPS LPS Milling, Grading & Paving
  • GPS Concrete Curb

Project Associate(s):

  • Kontur Geotechnical

Client Information:

  • CxP
    Art Penner - Construction Manager Civil Works
    T: 604-816-8329

Project Supervisor Information:

  • CxP
    Matt Buechler - Project Manager Roads and Rail
    T: 604-788-9662