All Roads Has Completed All Five Consecutive Phases of Hwy 1 Paving Projects for the BC Ministry of Transportation and Transit



A total of 264,858 metric tonnes of asphalt has been laid down to pave over 356.7 lane kilometers at the five busiest stretches of Hwy 1 in BC.


Highway paving is a unique responsibility, quite different from municipal or local road work, because highways must safely carry higher speeds and far greater traffic volumes. To ensure this, project specifications are far more demanding, and every step of the work is held to strict oversight and control.

As of fall 2025, we’ve been fortunate to contribute to five project phases under these rigorous requirements. With each phase, we’ve treated the experience as a chance to learn and improve — whether by adopting new technology, refining our methods, or finding more efficient ways to meet the highest engineering standards. It’s through this continuous learning, and the dedication of our teams, that we’ve been able to grow into a trusted leader in highway paving.


Did you know?


Every project awarded by the BC Ministry of Transportation and Transit comes with a demanding set of "End Product Specifications," which set the bar for quality paving in the province. These standards exist to make sure the roads we all rely on are smooth, durable, and built to last.

Since 2020, our team has worked through five project phases under these specifications. We're proud — and very grateful — that each one has earned the Ministry's End Product Specification Bonus.

For us, these bonuses aren't just about recognition. They're a reflection of the care our crews put into their work, the high standards the Ministry sets, and the shared goal of building safe, reliable infrastructure for communities across BC.

July 20, 2025

Phase 5

July - October 2025


From Cassiar Tunnel to Willingdon Avenue, Burnaby

  • 33,380 metric tonnes asphalt paved
  • 51.5 lane kilometers
  • End Product Specification Bonus: In-Progress

WATCH VIDEO   READ MORE

Phase 4

July - October 2023


From Brunette River Bridge to Port Mann Bridge, Coquitlam / Burnaby

  • 50,498 metric tonnes asphalt paved
  • 62.4 lane kilometers
  • End Product Specification Bonus: Awarded

WATCH VIDEO   READ MORE

September 23, 2023


October 15, 2022

Phase 3

July 2022 - May 2023


From Port Mann Bridge to Golden Ears Way, Surrey / Coquitlam

  • 84,520 metric tonnes asphalt paved
  • 110.4 lane kilometers
  • End Product Specification Bonus: Awarded
  • Here, we were the first in Canada to use TopCon's PaveLink system on major highway paving project!

WATCH VIDEO   READ MORE

Phase 2

June - October 2021


From Golden Ears Way to 216th Street Interchange, Surrey / Langley

  • 43,460 metric tonnes asphalt paved
  • 54.4 lane kilometers
  • End Product Specification Bonus: Awarded
  • Here, we were the first in BC to use echelon of 4 pavers and 2 milling machines side-by-side!

WATCH VIDEO   READ MORE

June 24, 2021


November 21, 2020

Phase 1

June - October 2020


From Willingdon Ave. to Gaglardi Way, Burnaby

  • 53,000 metric tonnes asphalt paved
  • 78 lane kilometers
  • End Product Specification Bonus: Awarded

WATCH VIDEO   READ MORE