Project has an Option for 2 - Additional 1 Year Terms (Potential Final Completion Fall, 2025)



Project #: 211184

Contract Value: $10,850,569.95

Status: In-Progress

Start Date: Winter 2021

Completion Date: Autumn 2025

Project Scope Highlights:

  • 76,807.50 Metric Tonnes of Asphalt Paving
  • 54,0000 of Full/Variable Depth Asphalt Milling + 600 Hours of Hired Milling Works
  • Over 2400 LM of Concrete Curb
  • Over 2100 m2 of Concrete Flatwork
  • 180,000L Of Asphalt Prime & Tack Coat
  • Over 360,000m2 of Asphalt Overlay Work
  • Asphalt Handwork, FOB Asphalt Sales, Weekend Work

Project Associate(s):

  • Kontur Geotechnical

Client Information:

  • City of Abbotsford
    Shane Kamstra - Project Manager
    T: 604-835-2642

Project Inspector Information:

  • City of Abbotsford
    Jesse Starting - Site Superintendent
    T: 604-853-5485

Project Engineers:

  • City of Abbotsford
    Engineering Department
    T: 604-853-2281