City of Coquitlam United Boulevard Rehabilitation


Date Posted : June 19, 2024

Print| Email a Friend| Back


United Boulevard in Coquitlam, BC underwent significant upgrades, including asphalt milling covering 17,500 m², asphalt paving totaling 5,360 MT, thermoplastic line painting, and the installation of 30 m of concrete curb & gutter and 30 m² of sidewalk construction.



Project #: 231361

Contract Value: $1,081,810.80

Status: In-Progress

Start Date: Spring 2023

Completion Date: Autumn 2023

Project Scope Highlights:

  • 17,500 m² of Asphalt Milling
  • 5,360 MT of Asphalt Paving
  • Concrete Curb & Gutter
  • Concrete Sidewalk
  • Thermoplastic Line Painting

Project Associate(s):

  • Bayhill Contracting Ltd.
  • Scottish Line Marking

Client Information:

  • City of Coquitlam
    Travis Hughes
    T: 604-218-5968