All Roads has been contracted by the Corporation of the Township of Langley to supply, deliver, and place asphaltic concrete, including asphalt grinding and replacement, for a one-year term starting June 1, 2024. The scope of work encompasses milling and placing asphalt on prepared bases or overlays at multiple locations across the township. Key project sites include 232 St at 56 Ave (Roundabout), 200 St from 66 Ave to 68 Ave (NB), 64 Ave from 197 St to 200 St (EB), Fraser Highway from 256 St to 260 St (EB), 200 St from 80 Ave to 84 Ave (SB), 16 Ave from 200 St to 208 St (EB), and segments along 96 Ave.
Project #: 241454
Contract Value: $1,328,130.00
Status: In-Progress
Start Date: Spring 2024
Completion Date: Summer 2024
Project Scope Highlights:
47,000 m² of Asphalt Milling
8,636 MT of Asphalt Paving
Client Information:
Township of Langley Mark Lohr - Project Manager T: 604-534-3211